1. 1. Are there holes Drilled in the
ROOF….what kind of impact does that have on our roof warranty?
a. We were told we had a 10 year no
leak warranty added to the roof.
ANSWER: YES, there are supports that are installed in places on RAFTERS and they are installed so there is no potential for leaks since they are sealed and SOLAR BEAR is a Licensed Roofing Company as well
2. 2. Can you provide us with Details
of what the Insurance policy for the $1,000,000 liability looks like (coverages
and exact policy type)?
a. Can you Recommend a company that
we should go through?
b. Can you allow us to contact
another customer to ask how they handled the $1,000,000 liability insurance
coverage that DUKE will require?
ANSWER: YES. they gave us the name of a Company that we can get the 1,000,000 Homeowners General Liability insurance through Gave us a Phone number and e-mail
3. 3. How many Hours of Sunlight does
the Panels need to generate full capacity. (16KW) –
A ANSWER: 4-6 hrs depending of time of year.
4. 4. Elements that go bad and maintenance
long term?
a. How long does an inverter last
(heard it was 25 years) and they cost about $5000
ANSWER: You have an Inphase - microinverter system.
ANSWER: You also have access to the APP to see production so you will know if there is something not functioning in the system. Duke has to monitor this also to determine your credit for putting power back into the system
ANSWER: also you have a 5 Year Wash clean annual contract, but after need to do wash clean annually, or you can setup a new contract.
5. 5. Can we have all the documents about warranty?
ANSWER: yes but also Solar Bear is in Partnership with Owens corning and we have our own Roofing License. In addition to SILFAB has a 25 year Product. Inclusive of labor
6.
7. 6. Can we walk through all of the next steps?
ANSWER:
a. Welcome meeting
b. Engineer Site Survey - Entry
Survey
c. Layout Design for Permitting
Completed.
d. Engineer Approval of permit
e. Layout Design Permit Submitted
f. Permit Approved
g. Schedule for Install
h. Install Day
i. HV Connecting panels to
Inverter.
j. Permit Inspection
k. Interconnection Setup….need
declaration
l. Duke Inspection (60 days)
m. Duke Cutover/Panel turn on
n. Once Swapped call solar bear – Exit
they walk through the system.